  • April 22 - May 22

    • Get in touch with the Tajo and the Kudu communities.

    • Analyze other storage modules like tajo-storage-hbase or tajo-storage-hdfs.

    • Analyze Kudu architecture.

    • Architectural drafting.

  • May 22 - June 22

    • Confirm the architecture.

    • Start to implement the actual code.

    • Implement KuduFragment

    • Implement KuduScanner/KuduAppenderImplement KuduTableSpace (part)

  • June 23 - July 30

    • Implement

  • KuduTableSpace (completion)
    • KuduScanner/KuduAppender

    • Implement

  • KuduFragment
    • KuduTableSpace 

    • Unit Tests

  • July 30 - August 15

    • Fix minor bugs

    • Write documentation.

...