Requirements and initial architecture was discussed between the 21st-24th of August 2004 in Colombo. It was decided that we prototype some of the identified components for a period of three months before a final plan for Axis 2.0 is prepared.

Prototyping

The following components are being prototyped:

High Level Plan

  1. Start Date: 25th August 2004
  2. Tentative End Date : 10th December 2004
  3. Integration and working prototype to be available on or before the 31st of December 2004

Milestone Release Plan for Axis2 01/M1

Sanjiva

Axis 2.0

Axis 2.0 Alpha

Axis 2.0 Beta

Axis 2.0 Final

Axis 2.1